200 A service upgrade with garage subpanel

A Standard-tier electrical estimate. The contractor sent eleven photos (meter, old panel inside and out, mast, roof line, garage, trench path), the panel schedule written on a napkin, and a 95-dollar hourly rate.

JobService upgrade 100 A → 200 A, overhead service, detached garage subpanel feed
LocationHouston, TX 77040
CurrencyUSD
Labor rateUS$95.00/h
Markup20%
TaxSales tax (materials) 8.25%
#ItemQtyUnitUnit priceHoursAmount
Service & panel
1 200 A main breaker load center, 40-space, NEMA 3R combo meter-main 1 ea US$480.00 4.0 US$480.00
2 Service entrance cable 4/0-4/0-2/0 AL SEU 30 ft US$6.20 1.5 US$186.00
3 Weatherhead, 2" rigid mast kit, straps, roof flashing 1 set US$165.00 1.5 US$165.00
4 Ground rods 8' × 2, clamps, #4 Cu GEC, water bond 1 set US$95.00 1.5 US$95.00
5 Breakers: 2P 20/30/50 A, 1P 15/20 A, AFCI/GFCI as required
16 circuits re-landed; 6 AFCI + 2 GFCI breakers
1 lot US$520.00 2.0 US$520.00
6 Whole-house surge protective device (Type 2) 1 ea US$110.00 0.5 US$110.00
Garage subpanel feed
7 60 A 2P feeder breaker 1 ea US$38.00 0.3 US$38.00
8 12-space 100 A main lug subpanel 1 ea US$85.00 1.5 US$85.00
9 #6-6-6-8 Cu URD / 1-1/4" PVC conduit, trenched 18" 65 ft US$7.40 7.8 US$481.00
10 Ground rod, bonding at detached structure 1 set US$45.00 1.0 US$45.00
General
11 Consumables: connectors, anti-oxidant, straps, labels, caulk 1 lot US$90.00 — US$90.00
12 Utility disconnect/reconnect coordination, inspection meeting 1 lot — 3.0 —
MaterialsUS$2,295.00
Markup (20%)US$459.00
Labor (24.6 h × US$95.00)US$2,337.00
Electrical permit (city, residential service change)US$150.00
SubtotalUS$5,241.00
Sales tax (materials) (8.25%)US$227.21
TotalUS$5,468.21

Options (not included)

ItemAmount
Generator interlock kit + 50 A inletUS$540.00
EV charger circuit 50 A to garage (NEMA 14-50)US$480.00

Assumptions and exclusions

  • Overhead service remains overhead; utility sets the new meter.
  • Existing branch circuits are re-landed as-is; no rewiring of the house included.
  • Trench in soil, no concrete cutting; customer restores landscaping.
  • Material prices are big-box retail at time of writing; labor at your stated crew rate.

Download Excel

Sample for illustration. Quantities, prices and hours are typical figures, not a quote for any real job.